You’re paying rent. When can your shop open?

What North Van Council’s vote means for building permits and business licences
You’ve signed the lease for your shop and rent has started. You need to book a contractor, order equipment and pick an opening day. How do you make those plans when you’re still waiting on a permit?
What did Council decide?
On November 16, City of North Vancouver Council voted unanimously to ask staff how to make building permits and business licences more predictable. Staff are due to bring back recommendations by June 30, 2027. Council would consider the proposed service standards after that.
What did Council ask staff to look at?
Where does the time go? Measure how long each type of application takes and show how much time is spent with the City, the applicant or an outside agency.
How long should it take? Recommend timelines and explain when the clock starts, pauses and resumes. The motion asks for a same-day or next-business-day target for low-risk business licences and renewals that don’t need an inspection or referral.
What do I need to submit? Give people clear checklists and guidance before they apply.
Where’s my file? Give applicants a way to see what’s missing, who has the next step and when they’ll hear back. Let them know if the date slips.
Is the City meeting its targets? Make a plan to publish results at least every three months. The motion also calls for an annual report once Council adopts service standards.
What’s getting in the way? Recommend changes to rules, fees or steps that slow applications down.
Where I’d start
I’d bring together the City staff who handle these files and the business owners, residents and builders who’ve applied. We’d walk through real applications to see where people lose time or have to chase an answer. Then I’d test changes on new files and ask staff to show in the June report what they heard and what changed.
If you’ve applied for a permit or business licence here, what’s the first thing you’d ask that group to fix?